Project: | 11KV INTERCONNECTION OF 2.0 MW BIOGAS POWER PLANT AT KAHANG, JOHOR FOR GREEN & SMART SDN. BHD. |
Services: | SUPPLY, DELIVERY, INSTALL, TESTING & COMMISSIONING OF 11KV INTERCONNECTION INCLUDING 11KV SWITCHGEARS, TRANSFORMERS, LV MAIN SWITCH BOARDS, 11KV OVERHEAD ABC CABLINGS ON 10m CONCRETE POLES (650m), LV UNDERGROUND CABLINGS TO 2 UNITS BIOGAS GENERATORS, FIBER OPTIC & INTERLOCKING SYSTEM. |
Owner: | Felda Palm Industries Sdn. Bhd. / Green & Smart Sdn. Bhd. |
Completion: | October 2015 – December 2016 |